Minutes:
Dr Sarah Groves-Phillips, Corporate Manager presented an
update on the phosphate risk register, which had since been downgraded to a
service risk and a general update on the ongoing work. In January 2021, Natural
Resources Wales (NRW) released advice to planning authorities on permitting
development in riverine catchments of Special Areas of Conservation (SAC)
across Wales. This guidance effectively placed an embargo on most development
within the river Teifi SAC catchment which encompassed over 50% of Ceredigion
and 3 of the 6 main towns. Ceredigion County Council added this constraint to
its corporate risk register shortly after and was forced to hold in abeyance a
number of planning applications and put the Local Development Plan preparation
on formal pause. An overview of the information shared at the Committee in
October 2024 was provided along with an update on the work in the past few
months as outlined in the report.
Nutrient Management had been on the Corporate Risk Register
for some time and whilst the work of the service in monitoring, delivering
improvements, leading by example had been comprehensive and had allowed some
capacity for development across the Teifi catchment alongside partner work by
Dŵr Cymru Welsh Water (DCWW) and NRW. This development opportunity was
still constrained and remained a critical challenge to economic growth. The
potential release of Marine SAC guidance was a real risk to the economic growth
of the county outside the Teifi catchment. Thus, it was important to continue
to include the Nutrient risk on the register and maintain momentum and critical
action on the project objectives. With that in mind, the risk register would be
reviewed regularly and actions updated as projects moved forward. An overview
of the current identified mitigating actions as outlined in the report was
provided.
Members were provided with the opportunity to ask questions
which were answered by Dr Sarah Groves-Phillips. The main points raised were as
follows:
·
It was not possible to directly compare
Ceredigion’s data on the river Teifi to NRW’s data, as the method of testing
was different. Citizens Science had been commissioned to undertake work, and
the results would be available soon. NRW had access to Ceredigion's data and
vice-versa, but it was not likely that NRW would use Ceredigion's data in their
analysis.
·
In response to a query related to whether there
was a notable difference in the levels of phosphate in the river Teifi
following the restrictions imposed on the agricultural sector in the past year,
it was noted that it was too early to say, and it would possibly take up to 7
years to come to a conclusion, however, the situation would be monitored. It
was acknowledged that the main source of phosphates was due to the wastewater
treatment plants.
·
The Nutrient Management Board (NMB) had not
undertaken modelling work on how the river Teifi would look in a decade,
however DCWW had done some work. Without a legislative framework in place, it
was difficult to ensure actions were carried out. A part of the NMB work
programme for the next year would include addressing gaps in data.
·
Although the NMB had not undertaken any
modelling on fish stock, NRW had done so and it appeared the fish stock had
declined.
·
From the Officer’s understanding, legal guidance
had been sought on the impact of the Marine SAC nationally prior to it being
released. The Planning Service awaited confirmation on whether they had been
successful in an SPF bid for additional funding to install water quality
monitors in the marine environment countywide. This would allow the local
authority to track nitrates in the Cardigan Bay SAC and develop mitigation
strategies.
·
To date, no work had been done on any other
river in Ceredigion due to funding, however, West Wales Rivers Trust operated
across the county. It was noted that local angling clubs had a wealth of
knowledge and could be invited to a future meeting if required. In terms of mine restoration, NRW had the
funding to undertake the work which was ongoing and would take time due to
legacy minerals.
·
From a planning perspective, connecting houses
to mains sewers was the preferred method, as there could be unintended
consequences of chemical dosing plants. Since 2019, Sustainable Drainage
Systems (SuDS) had been a requirement for any new housing development.
·
It was key that the local authority maintained a
healthy relationship with organisations such as NRW and DCWW to ensure
ambitions were driven forward. When data was published by other organisations,
it was a case of quality checking, and making a judgement on the data
available.
·
It was expected that DCWW would undertake the
work required at the water treatment plant to meet the permit by the end of
2026 as outlined in their Asset Management Plan, but no planning application
had been submitted to date. In response
to the Chair’s recommendation of writing a letter to DCWW to ask for assurance
that the plants would be upgraded, the Officer confirmed she was happy to draft
a letter if required.
·
The nutrient calculator developed by the NMB had
been recognised nationally and had been due to be released across Wales in June
2024, although this had been delayed to April 2025 to allow for data matching.
·
There were no outstanding planning applications
due to phosphates, although some applications that had been refused would have
possibly been approved prior to the advice received by NRW in January 2021.
·
The Officer noted it was difficult to score the
risk until the NRW guidance on the Marine SAC was released and the outcome for
Ceredigion. Once the guidance was published, Officers would be in a position to
review and put a plan in place.
Committee Members extended their thanks to Dr Sarah
Groves-Phillips and the team for their work.
It was AGREED to note the report.
Supporting documents: