Minutes:
Consideration was given to the update report on the Phosphate Situation
at the request of the Committee. Dr Sarah Groves-Phillips, Planning Policy
Manager provided Members with the background to the phosphate situation.
It was reported that currently, since the introduction of the interim
and revised guidance, the LPA had worked closely with neighbouring authorities
who share river catchments namely Carmarthenshire (Tywi) and Pembrokeshire
(Cleddau) to address the situation:
It was reported that since the introduction of the guidance, and
knowledge and expertise has developed in this area internally the LPA and were
now of the view that a multi-faceted strategy was required to ameliorate this
issue and were prioritising 4 distinct workstreams these are outlined below:
It was stated that as it was easy to assume that as the Council now know
the source apportionment work had confirmed the main source of phosphates was
from WWTPs its DCWW’s issue to resolve, unfortunately that was not a realistic
expectation. Whilst they were now obliged to consider solutions for the Teifi
more rigorously, it was still unlikely that Phosphate stripping would be
installed county wide due to the high costs and low density of populations among
other factors such as soli type river hydrology etc. Phosphate reduction
technology will be introduced into Llanybydder into AMP 7 but the type has not
yet been finalised and in accordance with their AMP procedures and timelines
finalising locations for wetlands in AMP 8, a final decision on this to date
had not been made. Its therefore important to consider all methods of phosphate
reductions thus the LPA are prioritising the following 4:-
(i) Short term measures to unlock development in the coming months-
creation of the nutrient calculator would allow developers to understand their
nutrient load – the mitigation guidelines would let them see how they could
‘spend’ that load. The GIS mapping would identify if that spend was worthwhile.
Unfortunately, there were not that many opportunities to ‘spend’ the load for
the scale of developments the council would receive, but they would continue to
investigate and amend the mitigation guidelines adding in new solutions as they
became available.
2.Medium term measures include utilising expert advice to establish
given the episodic failures of the Teifi monitoring whether there were any
water bodies in the catchment that consistently achieve (with headroom) their
targets so they could create a threshold under which they believe new
development would have limited impact on phosphate levels in that river
stretch. This meant this could say that housing/ tourism developments up to a
certain size would had little impact on the conservation objectives in XYZ
location and thus could come forward.
3.Longer medium-term measures include working with partners already
undertaking river restoration such as NRW to enhance their existing works and
thus create headroom within catchments for new developments. They were
currently working under the Habitats Regulations section 6 to procure a list of
all works being undertaken and then intend to source finance to multiply the
benefits of the existing schemes, utilising the regulatory powers of the
partner organisation. This would most likely be in the form of extending
riparian buffers which had the most measurable success in reducing phosphate
run off.
4.Long term measures include working with DCWW and any other interested
partners in over engineering constructed wetlands to not only meet the permit
requirements of DCWW WWTPs but also create headroom capacity for additional
housing and tourism developments in Teifi SAC catchment. Due to the long- term
planning of such developments including land acquisition, planning consent and
finance, this will take some time to realise but would ultimately be the most
cost-effective mechanism for delivering real solutions.
It was reported that there were a number of other potential mitigation
schemes that continued and each and every one was explored, whilst being
mindful of the limited viability of the region and thus trying to ensure all
measures were at the most reasonable cost to developers. This would of course
necessitate the authority or WG bearing the brunt of the costs, it was too
early to speculate what these may be, when this information was available the
appropriate reports would be prepared in due course.
The impact of the guidance on other service areas was also an important
consideration:
It was reported that following the revised guidance, the Development
Management service had prepared a developer toolkit to establish if they could
screen out any of the applications held in abeyance as now complying with
regulations relating to PTPs which under very specific criteria could now be
approved, however the parameters in which they were acceptable were quite tight
and thus this would not be a solution open to all. The service continues to
work through the backlog of cases and those newly submitted to screen out where
the guidance may apply and development could move forward. Given the
information requirements to be submitted by developers in order to meet the
requirements was fairly onerous this was a relatively slow process as tests of
likely significant effect and where necessary appropriate assessments (both
requiring ecology expertise) may still be needed to move to decision stage.
The ecology team were successful in a Heritage Lottery funding bid for
the Phosphates Reduction and Mitigation (PRAM) project. A project officer was
appointed (albeit behind schedule) and they were subject to the tight funding
timelines embarking on a programme of works to establish riparian buffers and
the feasibility of wetlands on public sector owned land. Unfortunately, this
project was devised before we understood the full extent of the issue and what
mitigations were best placed. Thus, in hindsight may had been delivered
differently never the less the overall outcome of the works was to deliver
Phosphate reductions in the Teifi SAC and this was welcomed.
It was likely at some point in quarter one of 2023 that the LPA would
receive a marine nutrient release for the marine SACs, as yet they did not know
what this would yield. It was anticipated that it would be related to failing
targets of nitrogen (a bigger concern in marine environments). The entire
Ceredigion coast was covered by 3 marine SACs (Cardigan Bay SAC, Penllyn &
Sarnau SAC and the West Wales Marine SAC) and if these SACs were failing their
targets and / or the guidance were to be released as it was in England it could
lead to a county wide embargo on development that increases waste water.
However, it’s important to note that the
LPA did not know what the marine release would say and / or if they are failing
the targets. Furthermore, all was not lost as the lessons learned from the
Phosphate release mean we were better placed to manage such an issue and had a
clear pathway for managing the impact. They also know that nitrogen was easier
to mitigate than phosphates and all the phosphate reduction works we were
planning to embark on also work for nitrogen. So, as we progress the work
streams we were also factoring in Nutrient monitoring and mitigations more
broadly than simply phosphates to nutrient stack our mitigations where this is
allowable.
The following were Future Workstreams:-
•Commissioning HRA specialist advice on NRW compliance report of the
Teifi, and where appropriate constructively challenging NRW in their role as
the nature conservation body
•Continued lobbying of WG and NRW in their role as environmental
regulator for provision of clarity of interpretation and clear leadership.
•Undertake strategic land use review of Authority’s assets to identify sites
for mitigation purposes – linking into disposal strategy and PRAM project.
•Identify & shortlist potential onsite and offsite mitigation
measures – gather evidence, produce high level, outline costs for shortlisted
mitigation schemes. incl. surface water separation, filter strips, planting,
wetlands – undertaking feasibility and technical appraisals and identifying
funding streams.
•Produce GIS Maps showing mitigation options.
•Develop strategy to deliver off-site mitigation schemes.
•Establish a framework for and develop and implement a Nutrient Credit
Trading System.
•Develop a Nutrient Management Supplementary Planning Guidance (SPG)
Incl. potentially enabling locally focused delivery.
•Explore potential for retro fitting RSL Housing Stock with water saving
measures to enable AH delivery.
•Develop a Water retention and reduction SPG.
•Develop opportunities for Grampian conditions and s106 agreements to
secure mitigation.
Following questions and comments from the floor, it was AGREED that an
update on the Phosphate Situation would be provided at the April 2023 meeting.
Supporting documents: