Minutes:
Consideration was given to the Report of
the
Corporate Lead
Officer Economy and Regeneration upon
development,
advertisement; local
authority and statutory planning
Applications:-
Ms Jane Morgan (Applicant) addressed the Committee in accordance with the
temporary addendum to the Operational procedure for Members of the Public
addressing the Development Control Committee in response to Covid-19
A210091 Retrospective planning application for agricultural implement and
storage shed and improvements to existing vehicular access, Land opposite Tan
Yr Allt, Coxhead, Tregaron
To DEFER determination of the application to request further
information from the applicant that she had presented at the committee.
A letter was read out on behalf of Mr Jeremey Davies
(Applicant) in accordance with the temporary
addendum to the
Operational procedure for Members of the Public
addressing
the Development Control Committee in response to
Covid-19
A210408
Internal alterations required to locate living accommodation at first floor and
bedrooms to the ground floor, fenestration alterations to rear elevation only,
Island House, Bellevue Gardens, Aberaeron
To APPROVE the application subject to
conditions.
A letter was read
out on behalf of Mr Rob Thomas (agent) in
accordance with the temporary addendum to the Operational
procedure
for Members of the Public addressing the
Development
Control Committee in response to Covid-19
A210573 Erection of new dwelling, Land adjacent to
Maes y Fedwen,Tresaith
To DEFER
determination of the application for the applicant to consider and agree to
an affordable dwelling, which would be secured via a Section106 agreement, with
the Corporate Lead Officer for Economy and Regeneration being authorised to
approve the application if agreed. In the event that the applicants do not
agree to an affordable dwelling, the application is to be referred to the Task
and Finish Group for a “cooling off” period.
Mr Richard Banks(Agent)
addressed the Committee in accordance with the temporary addendum to the
Operational procedure for Members of the Public addressing the Development
Control Committee in response to Covid-19
A210697 Variation of Conditions 4, 6, 7, 8 and 13 of
Planning Permission A160636 to substitute compliance with Indicative Site
Layout Plan RB/0054cREV4- March 2017 for Site Layout Plan reference
2538-505-REV B and Engineering Plan reference2538_(00)02_101-REV A, Land Off
Ffordd Newydd Aberporth, Cardigan, Cardigan
To APPROVE
the application subject to conditions and a Section 106 agreement.
Members wished to be noted that they had
raised the question if the applicant could provide further affordable dwellings
within the scheme. In response, the officer stated that the applicant had
provided three affordable in accordance with the policy.
A211113 Variation
of condition 3 of planning permission A160636 – to
extend the period
for submission of reserved matters, Land off Ffordd
Newydd, Aberporth,
Cardigan
To APPROVE
the application subject to conditions and a Section 106 agreement.
Ms Helen Ashby-Ridgway (Agent) addressed the
Committee in accordance with the temporary addendum to the Operational
procedure for Members of the Public addressing the Development Control
Committee in response to Covid-19
A210888
The proposed development of bases for the siting of static caravans and
modifications to the existing pond with associated access, car parking, landscaping and drainage
infrastructure works, Quay West Holiday Park Holiday Camp, New Quay
To DEFER
determination with powers given to the CLO to APPROVE the application subject
to conditions, subject to the HRA concluding that the proposed development
would not have an adverse impact on the Cardigan Bay and West Wales Marine
SAC’s.
Also that
a request be made to the company to instruct their users to use the main road
into New Quay to arrive at Milkwood and not through Llaingarreglwyd village.
A210914 Conversion of outbuilding into 2 holiday
units, Graig Farm, Mwnt, Cardigan
To APPROVE
the application, subject to conditions.
Members were of the opinion that the application
could be approved for the following reasons:-
o
Assists with complying to the Corporate Strategy
of the Council in boosting the economy and economic resilience
o
Planning Policy Wales was in favour of farm
diversification and rebuilding of existing buildings
o
The approval was Planning gain and an
improvement to the current buildings
o
The committee agree with Planning Policy Wales
paragraphs 5.6.10 and 5.6.11
A letter was read
out on behalf of Mr Alex Fox (Objector) and Mr Carwyn Young (on behalf of the
Council as applicant) addressed the committee in accordance with the temporary
addendum to the Operational procedure for Members of the Public addressing the
Development Control Committee in response to Covid-19
A210960 Internal refurb of existing leisure
centre external upgrade to principalelevation façade including
new curtain walling and signage. Internal works include additional room separation
and new partial first floor to include change of use from a leisure
centre (D2 use class), into a mixed use. Lampeter Leisure Centre, Peterwell
Terrace, Lampeter
To DEFER determination with powers
given to the CLO to APPROVE the application subject to conditions, subject to
the HRA concluding that the proposed development would not have an adverse
impact on the River Teifi SAC.