Minutes:
The Corporate Manager, Porth Cymorth Cynnar presented a report to the
Committee, which gave an update on the recent developments within the service.
The Committee were informed that the Service had been reviewing progress made
against the Ceredigion “Sport and Recreational Activity Strategy 2014-2020” in
preparation for the development of a new plan, which is due to operate from
2022-2027. It was noted that an initial public engagement exercise was underway
which will inform the development plan, forming the basis for the next stage of
the consultation process.
Lampeter Leisure Centre will be the location of the Council’s first
Wellbeing Centre, providing an enhanced range of Through Age Services to the
residents of Lampeter and mid county. Initially, Plascrug had been the intended
first centre, however due to Plascrug being utilised as a field hospital, the
Service were required to consider developing a Wellbeing Centre in another part
of the county. On the 1st of December 2020, Cabinet approved the
proposal to develop a Wellbeing Centre in Lampeter. The Service were eager to
ensure that the funding was not lost and could be utilised at another location.
Indicative costing suggest that construction costs may be met by grant
funding, although final costing will not be known until a tendering process has
taken place. It is anticipated that building works will be completed by June /
July 2022. The Leisure Centre will be
closed during building works however positive discussions have been had with
the University of Wales Trinity St David’s regarding the joint use of their
sporting facilities during this time.
The following questions had
been raised by Members:
·
Members noted
that concern had been raised by the Lampeter Lions Netball team that the
reduction to the size of the Hall from 4 to 3 badminton size courts was smaller
than that of a full-size netball court.
Officer noted that a letter had been sent to Lampeter Lions on Thursday
inviting them to meet with the Cabinet Member, the Corporate Lead Officer and
the Corporate Manager for Porth Cymorth Cynnar, however have not received a
response, as yet. It was noted that the
service have spoken to all the other clubs that use the Hall on a regular
basis, and no other objections were received. It was noted that the Netball
League meetings are held at Aberaeron and that the courts at Lampeter are used
for practice only. Facilities for practice will continue to be provided in the
hall. There are two further full-size outdoor courts available. Officer noted that the Council is in
discussion with the University of Wales Trinity St David, Lampeter with regards
to sharing their facilities whilst building work is carried out. The court
provided by the University is larger, being 1 metre short of a standards
netball court. It was noted that Wales
Netball Association is also developing the sport to include Walking Netball,
Seated Netball and Tiny Tots Netball, and the development of the Wellbeing
Centres will facilitate greater use of the centre by all of the residents.
·
Members asked
whether there are any guidelines in relation to size of courts. Officers noted
that the standard halls are 4 badminton size courts, however some halls are
smaller, others larger. There is no legal stipulation in relation to this.
·
Members asked
whether it would be possible to build an extension to the side of the building as
opposed to restructuring the internal layout. Officer noted that the grant
stipulated can be used to adapt assets for wider community use, to widen the potential
use of the asset in question, therefore this is not an option. It was noted that if the
grant funding is not spent, it would be lost.
·
Members noted
that they welcomed the provision of a Wellbeing Centre, however they did not
wish to see this happen, at the cost of losing the Sports Hall. They also
highlighted the need to consult with the youth of Ceredigion, as well as the
elderly. Officer noted that a review
carried out by ‘Just Solutions’ in 2018 noted that the building and provision
at the time was not sustainable. At that time discussions had taken place in
order to try and meet the needs of everyone including those of vulnerable
people and families and it was decided that the Leisure Centres could be
transformed into Wellbeing Centres to meet the needs of the residents in
Ceredigion. The Wellbeing Centres are
part of a wider strategy to improve the provision for people of all ages.
·
Members noted
that limited information had been provided regarding the proposed internal
restructure. Officer noted that the
development of the Wellbeing Centres are
an integral part of the Though Age and Wellbeing Programme and Strategy. The
Strategy and the Action Plan was shared with Members in a Scrutiny meeting on
Friday. The LA will be engaging with the community in order to raise their
awareness of the Strategy and the Action Plan.
·
The Cabinet
Member noted that information regarding the funding and the location of the
first Wellbeing Centre at Lampeter had been presented to Cabinet and that there
had been no call-in at that time.
·
Member noted
that the focus of such developments tended to be around the 3 main towns in
Ceredigion, and that areas such as Llandysul and Tregaron were losing out to
these towns. Officer noted that outreach
and pop-up provision would also be provided at other locations.
·
Members asked
whether the restructuring work would require planning permission, and whether
the new planning regulations resulting from high levels of phosphates on the
Teifi River Area of Special Conservation would restrict the development. It was recommended that a pre-planning
application is submitted.
·
Members asked
whether the Service was in consultation with neighbouring authorities with
regards to such provision. Officers
confirmed that this was in place.
The Chair of the Committee noted that he
would contact the Lions Netball team to advise them that the opportunity to
discuss their concerns was still available to them.
RECOMMENDATION:
Members agreed to
recommend the following to Cabinet:
·
The Committee respect that the decision
regarding developing the Wellbeing Centres has been made by
Cabinet.
The Committee does, however, recommend that all information provided by
Officers to Cabinet Members is fully shared with relevant Members. The
Committee also considers it important that information is also shared and views
sought from all stakeholders when appropriate.
Supporting documents: